Piling Works for A417 Missing Link Scheme
KIER TRANSPORTATION LIMITED · Awarded contract
AwardedPiling Works for A417 Missing Link Scheme
Awarded 01 Apr 2024
Awarded01 Apr 2024
Value£3,784,409.80
SupplierBAUER Technologies Limited
RegionSouth West
CategoryInfrastructure
Ended 1y 2mo ago1y 6mo term
Awarded 1 Apr 2024Expired 23 Sept 2025
About
KIER TRANSPORTATION LIMITED awarded a contract to BAUER Technologies Limited for piling works (contiguous, bored, and sheet piling) in connection with the A417 Missing Link at Air Balloon.
The scheme involved the design and construction of 3.4 miles (5.5 km) of new rural all-purpose dual carriageway connecting the existing A417 Brockworth bypass with the existing dual carriageway A417 south of Cowley.
The contract value was £3,784,409.8.
Similar open tenders12
TenderCloses
Bridge Bearings Design Support, Manufacture and Installation – Lower Thames Crossing Roads North (16 Structures)Infrastructure
13 Nov 2026
Highways Framework – Construction and Maintenance of Bridges, Drainage, Lighting and Traffic SystemsInfrastructure
30 Nov 2026
Boars Head Footbridge Superstructure Renewal Works – Wigan (2027)Infrastructure
20 Nov 2026
Kirklees Council Highway Structures Principal Inspections Contract (7 Dec 2026–6 Sep 2028)Infrastructure
09 Nov 2026
Access, Landscaping and Drainage Improvements at Acle Bridge Toilet Block – Broads AuthorityConstruction
03 Dec 2026
Design and Contract Administration for Three Playgrounds in Hounslow (Beaversfield, Bear Road, Crane Park)Construction
26 Nov 2026
Boars Head Footbridge Superstructure Renewal and Replacement – Wigan (2026)Infrastructure
20 Nov 2026
Blackdown Hills Green Finance Accelerator – River Wolf Weir Modifications, Floodplain Reconnection Designs and High‑Risk Water Quality Outfalls (South West England)Energy & Environment
30 Nov 2026
Design and Construction of Horse Fen & Somerton South Pumping Stations and Somerton Culvert – Upper Thurne Package 3Water & Sanitation
19 Jan 2027
South West Wales Regional Civil Engineering Contractors Framework 2027 – Appointment of Contractors for Civil and Specialist Civils Works across Carmarthenshire, Ceredigion, Neath Port Talbot, Pembrokeshire and SwanseaInfrastructure
26 Nov 2026
Supply and Install External Works and Soft Landscaping — Keogh Barracks, AldershotConstruction
16 Jul 2030
Retaining Wall Replacement and Highway Stabilisation – Waterloo Hill, LL22 8RH (Conwy)Infrastructure
19 Nov 2026
Other similar contracts12
Contract and supplierAwarded value
Sheet Piling Works for A417 Missing Link (Grove Farm) — Subcontract Awarded to Sheet Piling (UK) LimitedInfrastructureSheet Piling (UK) Limited
$241,330
Structures Formwork, Reinforcement and Concrete Works for A417 Missing LinkInfrastructureThames Valley Construction & Civil Engineering Limited
$7,560,352.95
Temporary Traffic Management Services for A417 Missing Link SchemeInfrastructureCore Highways (Projects) Limited
$2,812,552.41
Temporary CCTV Works for A417 Missing Link SchemeInfrastructureP&D Specialist Services Limited
$628,821.21
A417 Missing Link Series 600 Earthworks Subcontract Awarded to Walters UK LimitedInfrastructureWalters UK Limited
$46,934,912.56
Vehicle Recovery Services for A417 Missing Link SchemeTransport & LogisticsCore Highways (Projects) Limited
$1,063,552.92
Installation of Scheme Boards for A417 Missing Link at Air BalloonInfrastructureCrown Highways Limited
$16,310.36
Demolition Works for A417 Missing Link at Air BalloonConstructionCity Demolition Contractors (Birmingham) Limited
$124,794
A417 Missing Link Series 500 Drainage Subcontract Awarded to Hillstreet UK LimitedInfrastructureHillstreet UK Limited
$25,458,934.78
Temporary and Permanent Road Markings for A417 Missing LinkInfrastructureWJ North Limited
$389,951.19
Early Landscaping Works for A417 Missing Link at Air BalloonInfrastructureARB (tree Care Specialists) Limited
$470,000
Site Vegetation Clearance for A417 Missing Link Dual CarriagewayInfrastructurePracticality Brown Limited
$866,687.04
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.
–open infrastructure tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then £36/GBP per month
Revenue from government work£312K won so far