Demolition of Barshare and Hillside Primary Schools in Cumnock
East Ayrshire Council · Awarded contract
AwardedDemolition of Barshare and Hillside Primary Schools in Cumnock
Awarded Unknown
AwardedNot specified
Value£94,108.54
SupplierBardem Limited
AgencyEast Ayrshire Council
RegionScotland
CategoryConstruction
About
East Ayrshire Council awarded a contract to Bardem Limited for the demolition of the former Barshare Primary School and Hillside School in Cumnock, including basement boiler house, site strip, removal of internal roads, pathways, fencing, all items within the site boundary, and internal fixtures and fittings, with offsite disposal of materials.
The contract value was GBP 94,108.54 and the work was scheduled for 18 calendar weeks (16 weeks plus a 2-week Christmas shutdown).
Similar open tenders12
TenderCloses
Main Works Contractor for School Decarbonisation and Comfort Improvements – Bonner Mile End Primary School, Mile End (Tower Hamlets)Energy & Environment
30 Nov 2026
Demolition of Bell House, Barker House and Associated Garages – Stoke-on-Trent City CouncilConstruction
11 Dec 2026
Site Clearance, Demolition and Asbestos Removal — The Piggery, Beeches Woodland, CirencesterConstruction
31 Jan 2027
Decarbonisation and Comfort Improvement Works at Bonner Mile End Primary School, Mile EndEnergy & Environment
30 Nov 2026
Partial Demolition, Extension and Refurbishment of Glassford Community Hall – GlassfordConstruction
04 Dec 2026
Demolition of Bell House, Barker House and Associated Garages – Stoke-on-Trent City CouncilConstruction
11 Dec 2026
Construction of Single-Storey Extension and Internal Remodelling at Thameside Academy Alternative Provision BaseConstruction
30 Nov 2026
Demolition, Design and Construction of Howard's Lane Public Toilets – Wareham, DorsetConstruction
15 Jan 2027
EA RFCA Welwyn Garden City – Demolition of Cadet Buildings and Construction of New Joint Cadet CentreConstruction
18 Dec 2026
Design and Build of Additional Resource Base at Earls Hall Primary School – Southend-on-SeaConstruction
02 Dec 2026
Design and Construction of Four‑Bay Steel Workshop at Sidley Depot, Bexhill-on-SeaConstruction
07 Dec 2026
Demolition of Block Retaining Wall and Reinstatement with Gabion Wall – 17-23 St Georges Road, Dursley (GL11 4DN)Construction
04 Dec 2026
Other similar contracts12
Contract and supplierAwarded value
Demolition of Auchinleck Academy and Adjacent DwellingsConstructionBardem Limited
$395,000.03
Demolition of Four ASN Schools and Focus Centre in North AyrshireConstructionBardem Limited
$306,695.75
Demolition of Former Netherthird Primary School, CumnockConstructionCASKIE LIMITED
$88,763.13
Demolition of 2 Blocks at Quarry Knowe, AuchinleckConstructionBardem Limited
$25,572.8
Demolition of Garage Lock-ups at Barshare Road, CumnockConstructionDem-Master Demolition Limited
$12,641.75
Demolition of Bellfield Primary School, KilmarnockConstructionC.E.P. Demolitions Ltd
$66,477.08
Part Demolition of Eyemouth Primary & High School, Duns Primary School, and Edenside Primary SchoolConstructionGeorge Beattie & Sons Ltd
$243,663.62
Demolition of Technical Block at Cumnock AcademyConstructionC.E.P. Demolitions Ltd
$73,878.2
Demolition of Braeside Primary School and Janitor's Lodge by Central Demolition LtdConstructionCentral Demolition Ltd
$100,695
Demolition of Kinellar Primary School, BlackburnConstructionCentral Demolition Ltd
$101,040
Demolition of Former Gardenrose Primary School, MayboleConstructionCentral Demolition Ltd
$115,120
Demolition of Aitkenbar Primary School in DumbartonConstructionGeorge Beattie & Sons Ltd
$0
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.
–open construction tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then £36/GBP per month
Revenue from government work£312K won so far